The short answer
Build the shell first (footing, floor, 2x6 walls, roof and siding), have the electrician rough in the heater circuit, then line the room from the outside in: mineral wool, a taped foil vapor barrier, a 3/4 in air gap and the boards. The top bench goes 46 in below the ceiling, then the heater, its guard and the vents. For the 6 x 7 ft outdoor sauna in this guide that is 8 phases, about 80 hours for two people new to framing, and $8,751 in materials.
The example sauna
This guide follows the 6 x 7 ft outdoor sauna from the free plans. It has 294 cu ft inside, 305 with its window glass counted the way Harvia1 asks, a 8 kW heater rated 250 to 425 cu ft, a top bench at 38 in and 3 seats. Its materials come to $8,751 at the store prices we read. Open it in the designer to change any of it: every measure below follows.
The section that matters
Read it from the heater wall: the heater with the fresh-air intake low beside it, open floor, the lower bench at 20 in, then the top bench at 38 in, 46 in under the ceiling, inside the 43 to 51 in HUUM4 gives. The exhaust sits low on the bench wall and the drying vent high on it.
| Measure | This sauna | Where it comes from |
|---|---|---|
| Ceiling | 7 ft | HUUM manual range |
| Top bench | 38 in high, 5 ft 11-1/2 in long | 46 in below the ceiling |
| Floor to stand | 41 in | Our default, 30 in or more |
| Vents: supply, exhaust, drying | 6 in, 12 in, 4 in | Heater manual |
| Heater load | 33.3 A at 240 V | Conductors for 41.7 A, 125 percent |
The build, phase by phase
8 phases, each drawn at its end with its new parts in color. The hours are a planning estimate for two people new to framing; the electrician's hours are not in them.
Phase 1 of 8about 11 h, $986
Site, footings and floor
Site and footing. Mark a 7 ft 2 in x 8 ft 2 in footprint on level, drained ground. Lay the landscape fabric, dig and compact 6 in of paver base under each deck block, set the blocks level at the spacings on the foundation plan and string-line the skids (SK). Check your setback and permit rules first.
Floor. Set the 4x6 skids (SK) in the blocks, then the 2x6 rim joists (RJ) and floor joists (FJ) 16 in on center: 3 8d toenails per joist at each skid, 3 16d end nails through the rim into each joist. Square the frame by measuring the diagonals. Glue and screw the 23/32 tongue-and-groove floor, edges on joist centers, as the floor framing sheet shows. In a cold climate (the optional lines on the list), first fill the joist bays with mineral wool and nail the asphalt fiberboard under the joists to hold it and keep animals out. Then the tie-downs: screw an auger anchor from the tie-down kit into firm ground beside each corner of the skids and cable each skid end to it with two clamps, pulled snug.
Phase 2 of 8about 7 h, $581
Wall framing
Walls. Frame the four walls flat on the floor from the wall elevations: 2x6 studs (S, 81 in) at 16 in on center between a bottom plate (B1, B2) and a doubled top plate (P1, P2), corner backers on the front and back walls, 2 16d end nails per stud end. Frame the door opening at 28 in x 75 in in the heater wall: king studs, jacks (J), the header (H) and the filler (HF). Add the blocking at the heights shown (BK2 for the guard rails, BK3 laid flat behind the heater bracket), then stand, plumb and nail the walls together. Nail the upper top plate last: on the side walls it runs full length over the front and back walls' lower plates, and on the front and back walls it fits between, so the plates lap at every corner. Frame each window opening as its wall elevation shows: king studs, jack studs (NJ), the header (NH), the flat rough sill (NS) on its cripples (NC); 14-1/2 in x 28-1/2 in rough opening, sill 48-1/2 in up. Hold-down at the wall line ends (IRC R602.10.7): before the siding goes on, nail an LSTA18Z ZMAX strap tie from the list up the outside face of the front wall's king stud at the edge of its opening, 39 in from the front-right corner (outside), down over the plates onto the rim or end joist below: 6 of the 1-1/2 in strap nails into the stud and 6 into the joist. Glue with the construction adhesive and nail the plywood spacers (HS, NHS) between the header plies so each header is as thick as the 5-1/2 in wall.
Phase 3 of 8about 14 h, $845
Ceiling joists, rafters and roof
Ceiling. Set the 5 ceiling joists (CJ) 16 in on center across the 7 ft 2 in width, and the two end joists (CJE) tight against the inside of the front and back walls' top plates, so the ceiling boards end on framing. Then the 4/12 rafters (RF) at 16 in, one pair landing beside every ceiling joist; the pairs over the front and back walls have no joist and stand on the gable studs (GS), which sit on the top plates. Nail each rafter heel to its joist with 6 16d common nails (IRC Table R802.5.2(1) at 70 psf ground snow, the load the rafters, headers and skids are sized for, and checked: heel thrust 577 lb at 70 psf snow plus 10.5 psf dead (w x run / (2 x rise per foot of run)); a 16d common through the 1-1/2 in joist into the 1-1/2 in rafter carries 138 lb (NDS 2018 12.3.1, spruce-pine-fir, snow load duration 1.15), so 6 nails carry 827 lb): the joists are the ties that stop the rafters spreading the walls. A hurricane tie on every rafter (10 connector nails each) holds the roof down against wind; it does not resist the spread. Ridge board, gable studs, roof deck, underlayment, drip edge, closure strips and the metal roof panels, with butyl tape in every side lap, then the ridge cap over the top closures. Wrap the walls with the house wrap, lapped top over bottom, its laps and every cut around the door, windows and vents sealed with the house wrap tape, flash over the door head, then hang the T1-11 siding, caulk the trim and the door casing, and paint over one coat of exterior primer. Over every rafter pair, nail a 1-1/4 in x 20 gauge ridge strap across the top of the ridge board, three 10d common into the top edge of each rafter, the first at least 2-3/8 in from its end, before the roof deck goes on.
Phase 4 of 8about 9 h, $942
Wrap, siding and trim
House wrap, Siding and trim, Prime and paint. The last part of the step in the phase before covers this work.
Phase 5 of 8about 9 h, $762
Rough-in, insulation and foil
Rough-in. Your licensed electrician runs the dedicated 240 V heater circuit (33.3 A heater; conductors sized at 125 percent, 41.7 A or more), the light feed and the control or sensor cable, with 90 C copper wire inside the room. Cut the vent openings and set the duct sleeves (6 in supply, 12 in exhaust, 4 in drying) now. Get the rough-in inspected before you insulate.
Insulation and foil. Fill walls and ceiling with mineral wool. Staple the foil vapor barrier over the studs and joists on the warm (room) side of the insulation, shiny side into the room, seams lapped 2 to 3 in and every seam and every hole taped with foil tape. The foil is continuous: no plastic sheeting, ever.
Air gap. Screw 1x2 furring over the foil on every stud (F1) and every ceiling joist (F2) with 2-1/2 in screws. That 3/4 in gap behind the boards lets the wood dry; the heater maker asks for about 10 mm (1/2 in).
Electrician: heater circuit, light feed and sensor cable roughed in and inspected before the insulation.
Phase 6 of 8about 10 h, $1,734
Ceiling and wall boards
Ceiling boards, then walls. Before the wall boards, lay the sheet vinyl over the floor, turned up 4 in at every wall. Board the ceiling first, front to back, then the walls, horizontally from the top down so the last cut row lands behind the lower bench. Leave about 4 in (100 mm) between the bottom board and the floor and a small gap at the ceiling. Blind-nail through the tongues with stainless fasteners (galvanized can stain cedar). Western red cedar stays unfinished: no varnish or stain inside a sauna. Before the vinyl, build the heater floor zone (29-3/4 in x 19-5/8 in at the heater wall): cement board set in thinset and screwed, two coats of membrane lapped 2 in past its edge, then the vinyl over that lap; after the walls, tile the zone with dark grout and seal the ramp profile to the vinyl.
Phase 7 of 8about 15 h, $1,144
Benches, door and window
Benches. Top bench: it stands on its own legs and is never screwed to the wall, so the wall boards carry none of its load. Set the back rail (TR) against the wall boards and the front rail (TR), both with their tops at 31 in, on 20 legs (TL, 27-1/2 in), front and back at each support (the back legs at 0 in, 7 in, 14 in, 21 in, 42-3/4 in, 49 in, 56 in, 63 in, 70 in from the left end, one each side of the vent behind), then set the back rail doubler (TD) on the back legs tight against the front face of the back rail, 21 in to 44-1/4 in from the left end, tops flush, two 2-1/2 in screws into the rail at each end and none in between, lay the cross supports (TX) on edge across both rails, toe-screwed to each rail with two 2-1/2 in screws at each end, except the ones at 28 in and 35 in from the left end, which have no back leg under them: two toe screws into the front rail only, none into the back rail, so they rest on it, left edges at 0 in, 7 in, 14 in, 21 in, 28 in, 35 in, 42 in, 49 in, 56 in, 63 in, 70 in from the left end (the first and last flush with the bench ends), then the slats: 27-1/2 in + 3-1/2 + 5-1/2 + 1-1/2 in = 38 in to the seat. Lower bench: rails (WR) on 22 legs (WL, 9-1/2 in), top of rail 13 in, cross supports (WX) on edge, two toe screws into each rail at each end, left edges at 0 in, 7 in, 14 in, 21 in, 28 in, 35 in, 42 in, 49 in, 56 in, 63 in, 70 in, seat at 20 in. Screw its back rail to each front leg of the top bench with two 2-1/2 in screws so it cannot tip or slide; back them out to lift it for cleaning. Slats with 1/2 in gaps. Drive every slat screw up from below, 2-1/2 in long, so the point stops under the seat and no metal touches skin; on a cross support on edge, toe-drive them at 30 degrees through its top, two per slat, one from each face about 1 in in from each edge of the slat, started 1-1/4 in under its top: never bore its bottom edge, which carries the seat in tension. Use clear, knot-free boards where skin touches, and ease every edge.
Vents, light and door. Fit the covers over the vent sleeves: the 6 in supply in the side wall in front of the heater, the 12 in exhaust low on the back wall and the 4 in drying vent high on the same wall. Install the light under the top bench. Build the door core flat: two #9 x 3 in deck screws through each stile (D1) into each rail end (D2), driven from 1/2 in counterbores 2 in deep so each bites 1-1/2 in into the rail. Fit the diagonal brace (DZ) flat between the middle rail and the top rail, low at the hinge side, ends cut to the angle, two #9 x 3 in deck screws at each end. Then screw the face boards (DF) to every stile and rail on both faces with the 2 in screws; the screwed faces, the frame and the brace make the door stiff. Hang the door on 3 T-hinges, hinged on the right side as seen from outside (as drawn on the plan), centers 7 in from the top, 11 in from the bottom and midway; 1/8 in gap at the hinge and latch sides and the head, 1/2 in under it. Nail the stops (DS1, DS2) so the leaf closes flush, then the casing (DC1, DC2) on both faces. Handles and the roller catch on the latch side, 36 in up. The door opens outward and never locks. Window (14 x 28 in glass in a 14-1/2 in x 28-1/2 in rough opening): the glass is tempered and cannot be cut or drilled, so check the opening before it arrives. Nail the outside frame (NG) into the opening flush with the wall face, run a bead of clear silicone on it, set the glass on it with foam spacers to center it, then nail the inside frame (NG) and seal the glass to both frames with silicone; no screw or nail ever touches the glass. Trim both faces (NK), flash the head under the wrap and seal the outside casing. Every grille or louver larger than its sleeve sits on a cedar box (KB) 3-1/2 in deep around the sleeve end, so the air reaches the whole face. Under every Lambro 6 in hood, staple a square of the 1/4 in hardware cloth over the hole before the hood goes on.
Phase 8 of 8about 5 h, $1,757
Heater, guard, vents and light
Heater and guard. Mount the Harvia JH80B2401 with the heater side 5 in from the left wall boards, its bottom 7 in off the floor: the two 1-1/2 in lag screws supplied with the heater, 15-1/4 in apart, centered on the heater, 20 in off the floor, each left 1/4 in proud to hang the heater by its rear brackets, so its base hangs 7 in up (Harvia KIP manual Y05-1516 B (08/26), p. 20), each through the wall boards into the 1x2 backer (F3) on the flat backing (BK3), the hardware and depth the manual gives. Fit the thermostat bulb on the heater wall to the side of the heater away from the corner, about 14 in out from the heater and 14 in below the ceiling (Harvia KIP manual Y05-1516 B (08/26), p. 23), the capillary run up the wall under the trim pieces supplied, and have your electrician make the final connection. Build the guard: front rails (G1) 2 in clear of the heater front, side rail (G2) 2 in clear of its side, corner post (GP) 32 in tall. The rails butt into the post: two #9 x 3 in deck screws through the 1-1/2 in post into each front rail end, and two into each side rail end from 1/2 in counterbores 2 in deep in the post's front face, the pairs at different heights. At each wall end, a cedar 2x4 wall cleat (GW) stands 3-1/2 in out from the wall boards against the rail's outside face, away from the heater: two 2-1/2 in screws through the cleat into each rail's side, and two #10 x 4 in exterior screws per rail from 1/2 in counterbores 2-3/8 in deep through the cleat, the boards and the 1x2 backer (F4) into the blocking (BK2); every screw goes in square to the face it enters, never toed. The guard is a barrier against touching the heater; it carries no rated load. Stack the stones loosely by hand. Screw the two metal signs from the heater box in place (Harvia KIP manual Y05-1516 B (08/26), section 7.7, p. 24): the "REDUCE THE RISK OF FIRE" caution sign on the wall near the heater where it is easy to see, and the "REDUCE THE RISK OF OVERHEATING" warning sign outside the room, on the sauna door or next to it.
First heat. Work through the commissioning checklist in the builder's plan before you switch on. Then run the room empty for an hour with the vents open to burn off dust, check the thermometer at head height on the top bench, and enjoy it.
Electrician: final heater connection and the light.
Inspection and safety
Check before you continue
Inspection before you close the walls
In many towns the electrical rough-in is inspected before the insulation goes in. Check with your building department, schedule it if they want it, and do not cover a wire until it passes.
Safety
The heater circuit is the electrician's work
The 8 kW heater draws 33.3 A at 240 V for hours. The conductors are sized at 125 percent of that, the breaker and wire come from the heater's manual and the nameplate, and the cable inside the hot room must be heat-rated. A licensed electrician does it, under a permit where your town requires one. The sauna electrical guide has the breaker and wire for each heater size.
Depends on where you build
Ventilation is laid out, not calculated
The vents follow the heater maker's rules: supply low by the heater, exhaust low on the opposite wall, a drying vent high. Natural draft depends on your site and is not calculated. The ventilation guide has the sizes for every plan.
Tools you will use
- Circular saw and a miter saw for the boards and bench slats
- Drill-driver, a staple gun for the foil, a finish nailer for the boards
- Level, square, chalk line, tape measure
- A table saw helps rip the door jamb and the last board row, but a circular saw with a guide will do
Sources
Every number in this guide that does not come from our own sauna designer was checked against these 5 documents, numbered in the order the text first cites them and read between Oct 9, 2026 and Nov 16, 2026. 5 are heater makers, codes and stores.
- 1HarviaHow do I select the correct heater power?
- 2HarviaKIP heaters (KIP-30/45/60/80, B1 240 V): Instructions for installation and use, manual Y05-1516 B (08/26), the one edition this plan follows
- 3HarviaM3 wood-burning heater, US product page (WKM3)
- 4HUUMDROP 2.0 electric heater user manual (EU, v6)
- 5NFPA 70, National Electrical CodeArticle 424.4(B), branch-circuit sizing for fixed electric space-heating equipment (2020 text)